Wastewater Treatment Plant Expansion

Location

Fort Madison, IA

Owner

North American Packaged Foods Company

Engineer

Bolton & Menk

Services Provided

General Contractor

Contract Amount

$3.4M

Project Summary

Robinson was awarded a $3.4 million contract for the construction and start-up of a new wastewater aeration basin and final clarifier system for their long time food and beverage client at their facility located in Fort Madison, Iowa. Robinson’s scope for the project included demolition and removal of the existing equipment and materials such as miscellaneous piping and concrete pavement, as well as construction/installation of the pretreatment system including:

  • Aeration Basin
  • Chemical Feed Manholes
  • Scum Sumps
  • Clarifier
  • RAS/WAS Lift Station
  • Clarifier Effluent Manhole
  • Metering Manhole
  • WAS Valve Manhole
  • Lime Sludge Valve Manhole

Additionally, Robinson’s scope included installation of all equipment piping and valves; modifications to the existing clarifier control structure, sand shed, and clarifier effluent manholes; and all appurtenances.